Cutter Consortium recently conducted two surveys on software projects. One survey studied software project failures at more than 200 organizations and the other evaluated 232 recently completed projects around the world to determine what it means for a project to be successful.
Cutter Consortium Senior Consultants E.M. Bennatan and Khaled El Emam analyzed the results separately. The results will appear in a series of Executive Updates published by Cutter Consortium and written by Bennatan and El Emam.
Some preliminary findings include:
Software Project Failure Rates Based on Specific Criteria
Criterion | Failure Rate |
Customer satisfaction | 27% |
Ability to meet budget targets | 50% |
Ability to meet schedule targets | 55% |
Product quality | 28% |
Staff productivity | 32% |
Percentage of software projects in the past three years that were severely late (i.e., they overran their original schedule by more than 50%):
Percentage of respondents | |
None | 23% |
1%-10% | 37% |
11%-25% | 12% |
26%-50% | 10% |
51%-90% | 2% |
More than 90% | 1% |
I don't know | 15% |
Percentage of software projects in the past three years that were severely over budget (i.e., they overran their original budget by more than 50%):
Percentage of respondents | |
None | 24% |
1%-10% | 40% |
11%-25% | 15% |
26%-50% | 7% |
51%-90% | 1% |
More than 90% | 1% |
I don't know | 12% |